Construction progress: September 2025

by
Svitlo Park
13.10.2025

Construction progress: September

Building 8

  • Balcony installation is 90% complete
  • Ventilation installation is 70% complete
  • Aluminum structures installation on the 1st floor is 90% complete
  • Door installation on floors 3–18 is 80% complete
  • Finishing works in common areas on floors 4–10 are 50% complete
  • Basement finishing works are 50% complete
  • Heating equipment installation on floors 2–21 is 50% complete
  • Electrical installation in common areas on floors 2–21 — panels and cables — is 80% complete
  • Fire alarm installation is 50% complete

Building 7

  • Balcony installation is 100% complete
  • Basement plastering is 100% complete
  • Plastering on floors 1–16 is 100% complete
  • Screed installation on floors 2–16 is 100% complete
  • Fire alarm installation is 30% complete

Landscaping for Buildings 7–8

20% complete

Parking, Sections 1–6

  • Roofing works are 35% complete
  • Ventilation installation is 95% complete
  • Electrical installation is 90% complete
  • Video surveillance and access control system installation is 90% complete
  • Finishing works are 80% complete

Parking, Sections 7–8

Roofing works are 80% complete.