13.10.2025
Construction progress: September
Building 8
- Balcony installation is 90% complete
- Ventilation installation is 70% complete
- Aluminum structures installation on the 1st floor is 90% complete
- Door installation on floors 3–18 is 80% complete
- Finishing works in common areas on floors 4–10 are 50% complete
- Basement finishing works are 50% complete
- Heating equipment installation on floors 2–21 is 50% complete
- Electrical installation in common areas on floors 2–21 — panels and cables — is 80% complete
- Fire alarm installation is 50% complete
Building 7
- Balcony installation is 100% complete
- Basement plastering is 100% complete
- Plastering on floors 1–16 is 100% complete
- Screed installation on floors 2–16 is 100% complete
- Fire alarm installation is 30% complete
Landscaping for Buildings 7–8
20% complete
Parking, Sections 1–6
- Roofing works are 35% complete
- Ventilation installation is 95% complete
- Electrical installation is 90% complete
- Video surveillance and access control system installation is 90% complete
- Finishing works are 80% complete
Parking, Sections 7–8
Roofing works are 80% complete.