Construction progress: March 2025

by
Svitlo Park
04.04.2025

Construction progress: March

Building 7

  • Installation of K2 risers is 50% complete
  • Basement plastering works are 75% complete
  • Floor screed installation on floors 2–6 is 100% complete
  • Installation of underfloor heating pipes on floors 2–5 is 100% complete
  • Installation of underfloor heating manifolds on floors 2–5 is 100% complete

Building 8

  • Plastering works on floors 4–8 and 15–20 are 100% complete
  • Basement plastering works are 100% complete
  • Floor screed installation on floors 4–15 is 100% complete
  • Installation of underfloor heating pipes on floors 4–20 is 100% complete
  • Installation of underfloor heating manifolds on floors 4–20 is 100% complete

Parking, Sections 1–6

  • Ventilation installation is 90% complete
  • Fire alarm installation is 50% complete
  • Sprinkler fire extinguishing system installation is 100% complete
  • Floor installation is 80% complete
  • Electrical power supply installation is 20% complete