04.04.2025
Construction progress: March
Building 7
- Installation of K2 risers is 50% complete
- Basement plastering works are 75% complete
- Floor screed installation on floors 2–6 is 100% complete
- Installation of underfloor heating pipes on floors 2–5 is 100% complete
- Installation of underfloor heating manifolds on floors 2–5 is 100% complete

Building 8
- Plastering works on floors 4–8 and 15–20 are 100% complete
- Basement plastering works are 100% complete
- Floor screed installation on floors 4–15 is 100% complete
- Installation of underfloor heating pipes on floors 4–20 is 100% complete
- Installation of underfloor heating manifolds on floors 4–20 is 100% complete

Parking, Sections 1–6
- Ventilation installation is 90% complete
- Fire alarm installation is 50% complete
- Sprinkler fire extinguishing system installation is 100% complete
- Floor installation is 80% complete
- Electrical power supply installation is 20% complete