Construction progress: January 2025

by
Svitlo Park
13.02.2025

Construction progress: January

Building 5

  • Fire alarm system is 100% complete
  • Finishing works in common areas — painting, ceiling, overlays — are 100% complete
  • Video surveillance and access control system installation on floors 2–20 is 100% complete
  • Installation of the individual heating substation and pump station is 100% complete
  • Installation of window structures on the 1st floor is 100% complete
  • Common area works on the 1st floor are 75% complete

Building 6

  • Heating and ventilation installation on floors 2–23 is 100% complete
  • Water supply and riser installation is 100% complete
  • Sewerage installation — K1 and K2 risers — is 100% complete
  • Installation of the individual heating substation is 100% complete
  • Fire alarm system installation is 100% complete
  • MDF panel installation is 100% complete
  • Installation of window structures on the 1st floor is 100% complete
  • Common area works on the 1st floor are 90% complete
  • Landscaping for Buildings 5–6 is 80% complete

Building 7

  • Installation of K2 risers is 50% complete
  • Basement plastering is 50% complete
  • Floor screed installation on floors 2–4 is 50% complete
  • Installation of underfloor heating pipes on floors 2–5 is 50% complete
  • Installation of underfloor heating manifolds on floors 2–5 is 50% complete

Building 8

  • Plastering works on floors 4, 6, 7, 10, 14, and 16 are 100% complete
  • Basement plastering is 60% complete
  • Floor screed installation on floors 4–7 and 11–14 is 100% complete
  • Installation of underfloor heating pipes on floors 4–7 and 10–14 is 100% complete
  • Installation of underfloor heating manifolds on floors 4–7 and 10–14 is 100% complete

Parking, Sections 1–6

  • Ventilation installation is 80% complete
  • Fire alarm system installation is 25% complete
  • Sprinkler fire extinguishing system installation is 80% complete
  • Floor installation is 10% complete