13.02.2025
Construction progress: January
Building 5
- Fire alarm system is 100% complete
- Finishing works in common areas — painting, ceiling, overlays — are 100% complete
- Video surveillance and access control system installation on floors 2–20 is 100% complete
- Installation of the individual heating substation and pump station is 100% complete
- Installation of window structures on the 1st floor is 100% complete
- Common area works on the 1st floor are 75% complete
Building 6
- Heating and ventilation installation on floors 2–23 is 100% complete
- Water supply and riser installation is 100% complete
- Sewerage installation — K1 and K2 risers — is 100% complete
- Installation of the individual heating substation is 100% complete
- Fire alarm system installation is 100% complete
- MDF panel installation is 100% complete
- Installation of window structures on the 1st floor is 100% complete
- Common area works on the 1st floor are 90% complete
- Landscaping for Buildings 5–6 is 80% complete
Building 7
- Installation of K2 risers is 50% complete
- Basement plastering is 50% complete
- Floor screed installation on floors 2–4 is 50% complete
- Installation of underfloor heating pipes on floors 2–5 is 50% complete
- Installation of underfloor heating manifolds on floors 2–5 is 50% complete
Building 8
- Plastering works on floors 4, 6, 7, 10, 14, and 16 are 100% complete
- Basement plastering is 60% complete
- Floor screed installation on floors 4–7 and 11–14 is 100% complete
- Installation of underfloor heating pipes on floors 4–7 and 10–14 is 100% complete
- Installation of underfloor heating manifolds on floors 4–7 and 10–14 is 100% complete
Parking, Sections 1–6
- Ventilation installation is 80% complete
- Fire alarm system installation is 25% complete
- Sprinkler fire extinguishing system installation is 80% complete
- Floor installation is 10% complete